The wind farm lifecycle
-
Status: COMPLETE
Duration: 1 year
Discussions with landowners
Desktop studies of wind farm viability, with acess to historic wind data we can see there is enough wind to make the construction of a wind farm of this size feasible. We’re continuing to use a mobile wind monitoring unit (LiDAR technology) to measure wond speeds
Legal agreements for land use and access put in place
-
Status: IN PROGRESS
Duration: 1-2 years
Consultation with landowners, iwi and local communities
Site investigations, testing and modelling
Environmental impact investigations, including potential impact on people
Network connection application submitted to Transpower (completed March 2023)
Consent application to be lodged with council
Wind monitoring programme
Turbine procurement
-
Duration: 1.5-2.5 years
Civil earthworks, roads, foundations, and crane pads
Electrical works, underground cabling, transmission lines and substation
Transport of substation and turbine components to site
Installation and commissioning of wind turbines
Construction and environmental management plans: to minimise impact on people and place
Communicate project updates with community addressing any concerns
Remove temporary facilities and tracks once wind farm is operational
-
Duration: 30+ years
Wind farm provides electricity to national grid providing enough power for approximately 135,000 homes each year
Regular maintenance and operation activities occur at the site
-
Duration: 1-1.5 years
Decision made to either decommission site or upgrade equipment to continue operating
If decommissioned, turbines will be dismantled, removed and recycled where practical